Fettling Is Not Free: Why Rework Needs a Number on the Shop Wall

SSP Engineering
Fettling Is Not Free: Why Rework Needs a Number on the Shop Wall

Every fabrication shop runs two factories. The first is on the schedule: cutting lists, bend programmes, weld sequences, despatch dates. The second is unofficial, unpaid in the customer's eyes and almost never measured. It is the hour spent re-cutting a bracket because the revision was read from the wrong drawing; the afternoon spent persuading a twisted guard back to flat; the re-polish on a stainless panel that picked up a scratch in handling. Most managers know it exists. Very few can put a figure on it.

That gap between knowing and measuring is where margin quietly leaves the business.

Why rework stays invisible

Scrap is visible. A scrapped part is a physical event, it goes in the bin, and someone has to explain it. Rework is different: the part survives, it ships, the customer is satisfied, and the job is recorded as a success. The cost has simply been absorbed into the hours.

Three habits keep it there. First, estimators build in a contingency that everyone calls experience but which is, in practice, an unpriced rework allowance. Second, planned dressing and fettling is often bundled into the same mental category as genuine rework, so the signal is lost in the noise. Third, and most damaging, rework consumes capacity that no one has booked. A press brake spending Tuesday morning on corrective work is a press brake that is not earning on Wednesday's programme.

Rework is also a symptom, not a cause. It surfaces at the bench, but it usually originates in a drawing pack, a nesting decision, a bend deduction or an ambiguous tolerance. Measuring it at the point of discovery is the only way to trace it back.

Draw the line before you count

Before any tally begins, agree a definition. A workable one is this: rework is any time spent on a component or assembly, after it has passed a defined operation, to bring it back to specification because it did not meet that specification at first presentation.

That definition would normally include:

It should exclude dressing and fettling that the routing already plans for, first-off development work, and customer-initiated change. If the routing does not distinguish planned dressing from corrective work, that is the first thing to fix: the two must not share a cost code.

An A4 sheet beats a software licence

A four-week trial needs nothing more than a printed form, a pen and a named owner. One sheet per works order, handed in with the job card, with columns along these lines.

Field What goes in it
Date and works order Traceability
Part number and operation found at Where it surfaced
Operation that caused it Where it originated, if known
Defect description One sentence, plain English, plus a photo if useful
Root-cause code Single letter from a fixed list
Hours To the nearest quarter hour
Material or consumable cost Where measurable
Containment What was done to stop it reaching the customer

A short, fixed list of root-cause codes keeps the data useful. Something like: D for drawing or specification, N for nesting and programming, C for cutting, F for forming, P for fit-up and preparation, W for welding, S for surface and finishing, M for material and supplier, H for handling and transport, X for anything genuinely external.

Two disciplines matter more than the form itself. Hours must be recorded when the defect is found, not reconstructed from memory at month end. And the sheet must be completed by whoever discovers the problem, not by a supervisor guessing on their behalf.

The arithmetic that changes the conversation

Illustrative numbers are usually enough. Take a fourteen-person shop running a modest twenty-two rework hours a week, costed at a burdened rate of around £42 an hour. That is roughly £920 a week, or in the region of £42,000 across forty-six working weeks, before material, consumables and the cost of late delivery. It also represents more than a thousand hours of lost capacity.

Put that second figure to the management team. Ask what they would do with a thousand extra hours a year. The answer is usually a new machine, an extra fitter or the ability to take on one more framework contract. Framed that way, rework stops looking like an unavoidable overhead and starts looking like the cheapest capacity the business has access to.

Twenty minutes on a Friday

The review routine should be deliberately modest, because a routine that needs a meeting room and a projector will not survive a busy month.

  1. Twenty minutes, same time each week, on the shop floor, chaired by the fabrication supervisor with the cell leads present.
  2. Pareto the week by root-cause code. Identify the two largest and the one part family that recurs.
  3. Agree a single action with one owner and one date. One action, not five. Five actions is a wish list.
  4. Plot the rolling four-week average on a chart pinned to the wall next to the output figures. Four weeks smooths the noise; daily numbers invite over-reaction.
  5. Photograph the worst defect of the week and pin it beside the chart with a short caption explaining the cause, not the culprit.

One caution. Do not set a percentage target in the first month. A target of, say, three per cent encourages under-reporting long before it encourages improvement, and the data becomes worthless. Measure to learn for a quarter, then set a trajectory once the baseline is honest.

Reading the pattern

After four to six weeks, the codes tell a story. Where D dominates, the drawing pack is the problem: geometry defined only in a model, tolerances lifted from a template that was never appropriate, or revisions issued without a clear change note. Where F dominates, look at bend deductions, tooling condition and springback assumptions. Where P dominates, the issue is usually edge quality or a fit-up that is being forced rather than designed. Where W dominates, the question is heat input and sequence, which is a planning problem before it is a welder problem.

Repeat failures deserve particular attention. A defect that appears three weeks running in the same part family is not an operator error; it is a process that has been allowed to become normal.

The culture clause

The number will collapse within a month if it is used as a stick. Rework should be recorded by operation and root cause, not by individual. The message from the top has to be consistent and slightly boring: we are measuring the process, not the person, and the person who flags a problem early is doing exactly what we want.

That is the real argument for putting the figure on the wall. Not to embarrass anyone, but to end the fiction that the second factory is free. It is not. It is costing capacity, margin and, over time, the goodwill of the people who keep having to fix the same thing twice.

Start with a sheet of A4 on Monday. Four weeks of honest tallying will tell you more about your business than most capital investment cases.

All Articles

Related Articles

Model Behaviour: The Pre-Release CAD Audit That Protects UK Fabrication Margins

Model Behaviour: The Pre-Release CAD Audit That Protects UK Fabrication Margins

Stainless, Zinc or Powder? A Whole-Life Guide to Finishing UK Industrial Fabrications

Stainless, Zinc or Powder? A Whole-Life Guide to Finishing UK Industrial Fabrications

Held to a Higher Standard Than Necessary: The Hidden Cost of Excess Tolerance

Held to a Higher Standard Than Necessary: The Hidden Cost of Excess Tolerance